Scheduled for completion in 2020, The Berkeley will be an affordable mixed-income residential complex consisting of two five-story apartment buildings and a below grade garage. The buildings are standard construction wood framing, brick and cementitious panel with metal panel accents.

F&R’s project management, engineering and technical staff is on site providing materials testing and inspections during construction of the complex. Our services include inspection/monitoring/observation of the following:

  • Support of Excavation including piles, lagging, and tie-backs.
  • Waterproofing
  • Soils and Earthwork
  • Reinforcing Steel
  • Cast-in-Place Concrete
  • Post-Tension Concrete
  • Structural Steel
  • Masonry
  • Asphaltic Pavements
  • Spray-Applied Fireproofing

F&R’s geostructural monitoring team is also on site conducting precondition surveys of adjacent buildings and monitoring of SOE systems.